Tuesday, July 29, 2014

Referendum Update, July 29, 2014

ELEMENTARY PROJECT
The epoxy flooring installation in the new addition started today.  HVAC, temperature control, plumbing, and electrical contractors are coordinating to complete the final installation of our heating and cooling upgrades.  The system will be tested and balanced, and our maintenance staff will be trained by specialists.  The kitchen upgrades, cafeteria flooring, new door installation, ceiling grid installation, carpeting in the main office, and final clean up will need to be completed over the next three weeks.  By August 18, we expect to have access to a large portion of the new addition, and by August 25 we expect to have access to all new and remodeled spaces.   Mr. Alderson has created a shared document that will help each teacher know the specific time that they can expect to have access to their room.  As many of you know, Curt left the district.  We are relying on Rivercrest Technologies, our consulting firm, to aid in the completion of the technology installation needs for the project.  We hope to have a new Technology Director hired as soon as possible.  

7-28-14 New Addition Bathroom

7-28-14 Kindergarten Classroom

7-28-14 New Entrance into Multi-Purpose Room

7-28-14 New Hallway

7-28-14 Cafeteria

7-28-14 Addition Exterior

7-14-15 New Entrance

7-28-14 New Parking Lot


7-28-14 Storage Area

7-28-14 Student Coat Racks
7-28-14 New West Entrance
MIDDLE-HIGH SCHOOL PROJECT
The old boilers are almost completely removed and related demolition of piping and other materials continues.  The new boilers and other important materials have already been delivered.  Last Friday, we completed the electrical utility conversion to the new transformer that sits near the bus barn.  The utility poles have already, or will soon be coming down.  The new storm sewer system has been installed.  We are hopeful to have new blacktop behind the school prior to September 1.  Over the next two weeks, footings and foundation work for the new Ag-Tech wing will begin.
7-21-14 Storm Sewer Install
7-28-14 Project Sign on Schneider

7-28-14 Site work towards Schnieder

7-28-14 Site work towards MS-HS 


7-28-14 Storm sewer work

7-28-14 Utility Pole removal

7-28-14 