Monday, April 13, 2015

April 13, 2015 Referendum Update

4-13-15 Fitness Center

4-13-15 Fitness Center

4-13-15 Fitness Center

4-13-15 Fitness Center-Gym Entrance

4-13-15 New Wood Shop Entrance
Phase III:  Fitness Center
       Major developments over the past month include:
  • Removal of the old garage door;
  • New windows;
  • Painting;
  • Gym and exterior entrances;
  • Ceiling and fan installation;
  • New garage door into the existing wood shop;
  • Teachers’ lounge and Room 129C remodel.
       Major developments over the next month:
  • Flooring;
  • Operable wall partition; 
  • Casework;
  • New equipment;
  • The target date for substantial completion is May 15, 2015.
Phase IV:  Main Entrance/LMC
  • We will be shutting the HS LMC down on May 1.  The temporary storage location for the LMC is room 217.  As the fitness center work winds down, contractors will begin the work in the LMC.
  • Mike Huntzicker has volunteered to help with an auction.  The auction will be held on Saturday, May 23.  We will be selling equipment and furniture that can not be reused by the School District.  All items purchased will need to be removed no later than Sunday, May 24.  
  • Contractors have asked that the District be completely out of the construction zone by Tuesday, May 26. 