Wednesday, June 24, 2015

MS-HS Project, June 24, 2015

6-24-15 Main Entrance Addition
6-24-15 Main Entrance Addition
6-24-15 Main Entrance Addition
6-24-15 Main Entrance Addition
6-24-15 Main Entrance Addition
6-24-15 Main Entrance Addition
6-24-15 Room 224 Small Group Room Entrance
6-24-15 Room 224 Small Group Room


Wednesday, June 17, 2015

MS-HS Project Update, June 17, 2015

MAIN ENTRANCE ADDITION
    • Major developments over the past two weeks:
      • The demolition was a success.  The contractor had very few issues removing the old front entrance corridor.  The nice weather earlier in the month allowed the demo to be completed a few days early. 
      • The new "entrances" to the existing building are secure and each night a fence is setup around the construction site.
      • The connection between the new addition and existing cafeteria was created.
      • Footings for the new addition were poured.
      • Foundation walls are being constructed.  This process will take at least two additional weeks.
      • Major underground plumbing and electrical work will be done by the end of the week.
    • Goals for the next two weeks:
      • Water service will be reconnected to the high school building by the middle of next week.
      • Completion of footings and foundation work.
      • The floor for the new stairwell will poured.

    6-17-15 Main Entrance Addition
    6-17-15 Main Entrance Addition
    6-17-15 Main Entrance Addition
    6-17-15 Main Entrance Addition
    6-17-15 Main Entrance Addition
    6-17-2015 New Science Room Windows
    6-17-15 Main Entrance Addition
    6-17-15 Main Entrance Addition
    OLD LMC REMODEL
    • Major developments over the past two weeks:
      • Completed the demolition of existing mechanical and electrical materials.
      • Masonry work to completely separate the two rooms, create a new entrance to Room 223, and construct the break-out rooms.
    • Goals for the next two weeks:
      • Construction of sheetrock walls
      • Installation of doors and frames
      • Carpet and painting
    6-17-15 New Entrance to Room 223 (Mr. Hanley's new room)
    6-17-2015 Room 224 (Mrs. Michalek's Room)
    WOOD SHOP
    • Major developments over the past two weeks:
      • Removed old wood shop door and created a new entrance to Tech. Ed. classroom.
      • Poured the concrete ramp into the wood shop.
    • Goals for the next two weeks:
      • Complete the masonry work for the ramp and new classroom entrance.
      • Install doors and frames
      • Paint and floor patching
    6-17-15 New entrance to Tech. Ed. classroom
    6-17-15 Wood Shop Ramp
    6-17-15 Wood Shop Ramp

    Friday, June 5, 2015

    MS-HS Project, June 5, 2015

    6-5-15 Main Entrance Demo
    6-5-15 Main Entrance Demo
    6-5-15 Main Entrance Demo
    6-5-15 Main Entrance Demo
    6-5-15 Main Entrance Demo
    6-5-15 Entrance to Cafeteria
    6-5-15 Entrance to Cafeteria
    6-5-15 Old LMC Remodel
    6-5-2015 Old LMC Remodel
    6-5-2015 Ramp to Wood Shop

    Tuesday, June 2, 2015

    MS-HS Project, June 2, 2015

    The demolition of the main entrance corridor began early on June 1, 2015.   Last week contractors completed interior demolition, disconnected mechanical, electrical, and plumbing systems, and shut off water to the entire building.  We are hoping that the exterior demo will be complete by the middle of next week.   After the demolition is complete crews will be working to create the footings for the first floor of the addition.  In addition to the demo work, a ramp is being added to make the existing wood shop accessible and the old LMC is being remodeled into two large classrooms.
    6-2-15 MS-HS Demo
    6-2-15 MS-HS Demo
    6-2-15 MS-HS Demo
    6-2-15 MS HS Demo
    6-2-15 MS-HS Demo
    6-2-15 MS-HS Demo
    6-2-15 MS-HS Demo
    6-2-15 MS-HS Demo