Tuesday, June 2, 2015

MS-HS Project, June 2, 2015

The demolition of the main entrance corridor began early on June 1, 2015.   Last week contractors completed interior demolition, disconnected mechanical, electrical, and plumbing systems, and shut off water to the entire building.  We are hoping that the exterior demo will be complete by the middle of next week.   After the demolition is complete crews will be working to create the footings for the first floor of the addition.  In addition to the demo work, a ramp is being added to make the existing wood shop accessible and the old LMC is being remodeled into two large classrooms.