Wednesday, June 17, 2015

MS-HS Project Update, June 17, 2015

MAIN ENTRANCE ADDITION
    • Major developments over the past two weeks:
      • The demolition was a success.  The contractor had very few issues removing the old front entrance corridor.  The nice weather earlier in the month allowed the demo to be completed a few days early. 
      • The new "entrances" to the existing building are secure and each night a fence is setup around the construction site.
      • The connection between the new addition and existing cafeteria was created.
      • Footings for the new addition were poured.
      • Foundation walls are being constructed.  This process will take at least two additional weeks.
      • Major underground plumbing and electrical work will be done by the end of the week.
    • Goals for the next two weeks:
      • Water service will be reconnected to the high school building by the middle of next week.
      • Completion of footings and foundation work.
      • The floor for the new stairwell will poured.

    6-17-15 Main Entrance Addition
    6-17-15 Main Entrance Addition
    6-17-15 Main Entrance Addition
    6-17-15 Main Entrance Addition
    6-17-15 Main Entrance Addition
    6-17-2015 New Science Room Windows
    6-17-15 Main Entrance Addition
    6-17-15 Main Entrance Addition
    OLD LMC REMODEL
    • Major developments over the past two weeks:
      • Completed the demolition of existing mechanical and electrical materials.
      • Masonry work to completely separate the two rooms, create a new entrance to Room 223, and construct the break-out rooms.
    • Goals for the next two weeks:
      • Construction of sheetrock walls
      • Installation of doors and frames
      • Carpet and painting
    6-17-15 New Entrance to Room 223 (Mr. Hanley's new room)
    6-17-2015 Room 224 (Mrs. Michalek's Room)
    WOOD SHOP
    • Major developments over the past two weeks:
      • Removed old wood shop door and created a new entrance to Tech. Ed. classroom.
      • Poured the concrete ramp into the wood shop.
    • Goals for the next two weeks:
      • Complete the masonry work for the ramp and new classroom entrance.
      • Install doors and frames
      • Paint and floor patching
    6-17-15 New entrance to Tech. Ed. classroom
    6-17-15 Wood Shop Ramp
    6-17-15 Wood Shop Ramp