Wednesday, July 15, 2015

MS-HS Project, July 15, 2015

MAIN ENTRANCE/LMC
Major developments over the past two weeks:

  • Water service to the MS-HS has been reconnected with a new meter and pressure booster system.
  • Footings, foundation, and underground electrical and plumbing are complete.
  • 1st and 2nd floor concrete floors have been poured.
  • Steel joist and metal decking for the 1st and 2nd floor is complete.
  • Interior masonry walls are complete.

Major development over the next two weeks:

  • The installation of the roof will begin on July 20.  
  • Exterior brick will be begin no later than July 20.
  • 1st floor gypsum board wall assembly.    

The recent rain has slowed progress.  The project is about 5 days behind schedule, however, the building will be ready enough for classes on September 8th.  Any aspects of the project that are not complete by September 8 will not inhibit the start of the 2015-2016 school year.

OLD LMC CLASSROOMS AND WOOD SHOP REMODEL
Major developments over the past two weeks:

  • Construction of breakout learning rooms and technology closet.
  • Installation of new doors and frames.
  • Painting
  • Ceiling
  • Installation of recycled casework 

Major development over the next two weeks:

  • Carpet and Floor patching
  • Furniture
7-14-15 Main Entrance

7-14-15 Main Entrance 
7-14-15 Main Entrance 
7-14-15 Main Entrance 
7-14-15 Main Office

7-14-15 Main Office from Lobby
7-14-15 Main Entrance Lobby/Mrs. Schmitz's Room